Participatory budgets 2020-2021
#EsparregueraDecideix
Execution works winning proposals - Participatory Budgets 2018-
* The proposals are ordered due to the date of execution of the works:
1. TENNIS WEDDINGS
Site:
Objective and description of the work:
Reform of the changing rooms of the Esparreguera tennis club:
• Demolition of partitions, disassembly of buildings, doors, sanitary ware, false ceiling, removal of existing furniture and correct management of the generated waste.
• Formation of new walls, provision and installation of doors and screens, and modernization of supply services.
• Sanitation and repair of the existing channel in the area of the football field, repair of existing cracks and open horizontal seal.
Current state of works:
Complementary information:
1. Adjudicator Company: SOLUTIONS FOR THE BUILDING 2013 SL
2. Date Adjudication: 12/31/2018
3. Start of execution of the works: February 13, 2019
4. Number of votes proposed: 103 votes
2. ACCESSIBLE AND SAFE SCHOOLS
Site:
Objective and description of the work:
The planned works on the Carrer de la Gorgonçana will allow the accessibility and security of the school pathway to be guaranteed, among others, the following actions:
• Atrium: The length of the existing atrium will be increased, incorporating a railing with a length.
• Improvement of sidewalks and Bus stop: The sidewalk will be extended in front of the IES El Cairat and incorporate a stop pole with information on the line.
• Improvement Signaling and Urban Furniture.
Current state of works:
Complementary information:
1. Awarded Company: MOIX SERVEIS I OBRES SL
2. Date Adjudication: 12/31/2018
3. Start execution of the works: March 4, 2019
4. Number of votes proposed: 106 votes
3. INCLUSIVE GAMES FOR CHILDREN
Site:
PLAÇA DEL CENTRE
PLAÇA DEL REI
Objective and description of the work:
Performances will take place at Plaça del Rei, Plaça del Centre.
Plaça del Rei: Restore the top layer of existing rubber flooring in poor condition, taking into account the thicknesses and qualities appropriate to the regulations, remove the existing foundation and install inclusive playful elements:
• Multi-activity activity accessible and inclusive: for children from 2 years.
• Swing with basket seat for children between 4 and 10 years, with a free fall height of not more than 1,50 m.
• Individual spring set with backrest and lateral protections for children between 2 and 6 years, with a free fall height of not more than 50 cm.
Plaça del Centre: Installation of the following playful elements:
• 3 touch panels.
• Twister: painting on the floor.
Complementary information:
1. Adjudicator Company: Games KOMPAN S.A.
2. Date Awarded: JGL 3/20/2019
3. Forecast for the execution of the works: April.
4. Number of votes proposed: 105 votes
4. WALKING ROAD AND BIKE RAIL BACK TO THE ROAD B-231
Site: